Construction Submittal Log Template: Columns That Work

Updated 7 min read

Short answer

A construction submittal log lists every submittal the specs require, with its spec section, type, responsible party, dates and review status. Build it from Division 1 and each spec section's submittal article, then update it at every transmittal.

Submittal types in spec Section 01 33 00
Action and informational
UFGS 01 33 00 (wbdg.org)
Status codes on one state DOT register
A, C, R, D
Alaska DOT Form 25D-030
Submittals are contract documents?
No
AIA A201 Section 3.12
On this page (7)
  1. The submittal log template: columns to copy
  2. Build the log from the specs, not from memory
  3. Action vs. informational submittals
  4. Status codes to use in the Action column
  5. Keep the log current
  6. Common mistakes
  7. Common questions

A construction submittal log is a table that tracks every submittal the contract requires, from the first transmittal to the final review response. Each row is one submittal. Each column answers a question someone will ask in a coordination meeting: what is it, who owes it, where is it, and can we buy the material yet. The template below gives you the columns, and the sections after it explain how to fill them in from your specs.

The submittal log template: columns to copy

Paste this header row into Excel or Google Sheets and you have a working log.

ColumnWhat goes in it
Log no.Your own running number, unique per project
Spec sectionCSI section the requirement comes from, for example 08 11 13
Spec paragraphThe article or paragraph that calls for the submittal
DescriptionPlain-language name: "Hollow metal frames, shop drawings"
TypeAction or informational (see below)
SubtypeShop drawings, product data, samples, mockup, certificate, test report
Responsible sub or supplierWho prepares it
Required byThe date you need approval to protect the schedule
Date receivedWhen it reached the general contractor
Date sent to reviewerThe transmittal date to the architect or engineer
ReviewerArchitect, structural, MEP, or other consultant
Date returnedWhen the review response came back
ActionReview status code (see below)
Resubmittal no.Revision count: R0, R1, R2
NotesConditions, open comments, linked RFI

Log no.

What goes in it
Your own running number, unique per project

Spec section

What goes in it
CSI section the requirement comes from, for example 08 11 13

Spec paragraph

What goes in it
The article or paragraph that calls for the submittal

Description

What goes in it
Plain-language name: "Hollow metal frames, shop drawings"

Type

What goes in it
Action or informational (see below)

Subtype

What goes in it
Shop drawings, product data, samples, mockup, certificate, test report

Responsible sub or supplier

What goes in it
Who prepares it

Required by

What goes in it
The date you need approval to protect the schedule

Date received

What goes in it
When it reached the general contractor

Date sent to reviewer

What goes in it
The transmittal date to the architect or engineer

Reviewer

What goes in it
Architect, structural, MEP, or other consultant

Date returned

What goes in it
When the review response came back

Action

What goes in it
Review status code (see below)

Resubmittal no.

What goes in it
Revision count: R0, R1, R2

Notes

What goes in it
Conditions, open comments, linked RFI

You can add a lead-time column for long-lead items, and a "delegated design" flag for anything that needs a stamped engineer's calculation. Don't add columns nobody will fill in. A log with blank columns stops being trusted.

Build the log from the specs, not from memory

The log starts life as a list of what the contract requires. It is not a list of what subs happen to send you.

  1. Read Section 01 33 00, Submittal Procedures. In a CSI-format project manual this is where the project's rules live: how many copies, how transmittals are numbered, review durations, and whether action and informational submittals travel separately. Many versions require action and informational submittals from the same spec section to go in separate packages with separate transmittals (UFGS 01 33 00). If your spec says so, your log needs separate rows.
  2. Open every technical spec section and find its submittals article. Each item listed there is one row.
  3. Add Division 1 items such as the schedule of values, the construction schedule, and the safety plan if the spec treats them as submittals.
  4. Assign each row to the sub or supplier who owns the work, so there is a name against every line.
  5. Back-schedule the "Required by" date. Work backward from the date the material must be on site: fabrication time, then review time, then the time to prepare and check the package.

Some specs include a blank submittal register as an attachment. The Unified Facilities Guide Specification, for one, includes a Submittal Register as Attachment A to its 01 33 00 section. If yours does, use it as the starting point and add the columns above it lacks.

Consultants, files and deadlines in one place. Run this project in Olumba →

Action vs. informational submittals

Specs split submittals into two types, and the type decides whether work can proceed.

TypeWhat it isDoes work wait for the review?
ActionWritten and graphic information that needs the design team's responsive actionYes. Don't fabricate or install until it is acted on
InformationalInformation the design team receives but doesn't approve, such as certificates or reportsUsually no. One lab's spec says review is needed for acceptance, but work may proceed before review

Action

What it is
Written and graphic information that needs the design team's responsive action
Does work wait for the review?
Yes. Don't fabricate or install until it is acted on

Informational

What it is
Information the design team receives but doesn't approve, such as certificates or reports
Does work wait for the review?
Usually no. One lab's spec says review is needed for acceptance, but work may proceed before review

These definitions are paraphrased from project specifications that follow the CSI model, including Los Alamos National Laboratory's 01 33 00. Your project's own wording governs. Read it before you rely on this table.

The contract language backs the same sequencing. Under AIA A201 Section 3.12, the contractor may not perform work that requires a submittal and review until the submittal has been approved. The A201 also says submittals are not Contract Documents, and that the architect's approval does not relieve the contractor of deviations from the contract unless the contractor specifically identified them. Check the edition in your contract, because 1997 and 2017 wording differs. See the AIA Contracts guide to A201 Section 3.12.

Status codes to use in the Action column

There is no single national standard. Most projects use a version of four responses. Alaska DOT's submittal register, for example, uses status codes A (approved), C (conditionally approved as noted), R (resubmit, insufficient information for review) and D (disapproved or rejected) (Alaska DOT Form 25D-030). Other projects write them out.

CodeTypical meaningCan the sub proceed?
Approved / No exceptions takenConforms in generalYes
Approved as notedConforms if the marked corrections are madeYes, following the notes
Revise and resubmitNot enough information or not acceptable as shownNo. Resubmit first
RejectedDoesn't comply with the contract documentsNo. Submit compliant material

Approved / No exceptions taken

Typical meaning
Conforms in general
Can the sub proceed?
Yes

Approved as noted

Typical meaning
Conforms if the marked corrections are made
Can the sub proceed?
Yes, following the notes

Revise and resubmit

Typical meaning
Not enough information or not acceptable as shown
Can the sub proceed?
No. Resubmit first

Rejected

Typical meaning
Doesn't comply with the contract documents
Can the sub proceed?
No. Submit compliant material

Use whatever vocabulary the spec uses. If the spec lists the codes, copy them exactly. Don't invent your own, because the reviewer's stamp has to match the log.

One caution from practice. Reviewers sometimes overuse "approved as noted" on items that really need another look, such as control sequences. An ACHR News column argues those should come back as revise and resubmit (ACHR News). As the person keeping the log, you can flag an "as noted" return that has more than a couple of comments and ask whether a resubmittal is the safer path.

Keep the log current

A log is only useful if it matches what happened yesterday. A few habits do most of the work.

  • Update at every transmittal. Log the date in when a package arrives and the date out when it leaves. Don't batch this to Friday.
  • Log the resubmittal as a new revision of the same row. Keep the history. When a dispute comes up about who held the submittal, the dates answer it.
  • Review the log weekly against the schedule. Sort by "Required by" and look at everything not yet returned.
  • Flag the long-lead items first. If switchgear, elevators or curtain wall are late in the log, they are late on the schedule.
  • Reconcile with the field. Before anything is installed, check that its row shows an approved status.

If you run many projects, a shared tracker beats per-job spreadsheets. Olumba tracks project documents in one place (pricing), and the FAQ covers related questions.

Common mistakes

  • Building the log from what subs send. You will miss the submittals nobody remembered. Start from the specs.
  • One row for a whole spec section. Split by item. A single "Doors" row hides that the hardware set and the frames are on different timelines.
  • No "required by" date. Without it you can't tell which late item matters.
  • Mixing action and informational items in one transmittal when the spec forbids it.
  • Letting "approved as noted" close the row without confirming the sub saw the notes.

Common questions

What is a submittal log in construction?

It is the project's master list of required submittals and where each one stands. It records the spec section, who owes it, key dates, and the review result. It is usually kept by the general contractor's project engineer or project manager.

What is the difference between a submittal log and a submittal schedule?

The log tracks status: what has been sent, returned or approved. A schedule sets the planned dates for submittals so review time fits the construction schedule. Many teams combine them by adding a "required by" column to the log. Some specs ask for the schedule as its own submittal.

Who creates the submittal log?

Usually the general contractor, from the specifications. Some specs require the architect to provide an initial register, as in the UFGS model. Either way, the contractor maintains it through construction.

What should a submittal log include at minimum?

A unique number, the spec section, a description, the responsible party, the dates sent and returned, and the review status. Everything else in the template above is useful but optional.

Can I use Excel for a submittal log?

Yes. A spreadsheet is fine for a small project with one person updating it. It gets harder with many contributors, so move to a shared tool when more than one person edits at once.

Do informational submittals go in the log?

Yes. They are still required by the specs, and the owner may ask for proof that the certificate or report was delivered.