Construction Survey: Types and When You Need One
Updated 6 min read
Short answer
A construction survey locates the designed building, grades and utilities on the ground with stakes, then checks the work as it goes. Boundary, topographic, foundation and as-built surveys are separate products, and your building department's checklist says which it wants.
- Foundation survey deadline (Alcoa, TN)
- 15 days after approved footing inspection
- City of Alcoa foundation survey requirement
- Minimum building-corner stakes (Monterey County, CA)
- 4 wooden stakes
- Monterey County staking page
- ALTA/NSPS standards effective
- February 23, 2021
- 2021 ALTA/NSPS Minimum Standard Detail Requirements
On this page (7)
A construction survey is the surveying work that turns the plans into marks on the ground and checks that the finished work matches. It sets the horizontal and vertical control points, then stakes building corners, grades and utilities so the crew builds in the right place. It is not the same document as the boundary survey you submit with a permit application, and mixing the two up is how projects get stopped at the footing inspection.
This guide separates the survey types, explains what staking delivers, and shows how building departments trigger each one.
The survey types, side by side
Several products get called "a survey." They answer different questions and arrive at different points in a project.
| Survey | What it answers | Typical timing |
|---|---|---|
| Boundary survey | Where are the legal property lines? | Before design and permit application |
| Topographic survey | What are the elevations, contours and existing features? | Before design, and for grading or drainage review |
| Construction survey (staking) | Where do the corners, grades and utilities go on the ground? | During construction |
| Foundation survey | Does the poured foundation sit where the design says, in location and elevation? | After footings or foundation, before framing |
| As-built survey | Where did the finished work actually end up? | After construction |
Boundary survey
- What it answers
- Where are the legal property lines?
- Typical timing
- Before design and permit application
Topographic survey
- What it answers
- What are the elevations, contours and existing features?
- Typical timing
- Before design, and for grading or drainage review
Construction survey (staking)
- What it answers
- Where do the corners, grades and utilities go on the ground?
- Typical timing
- During construction
Foundation survey
- What it answers
- Does the poured foundation sit where the design says, in location and elevation?
- Typical timing
- After footings or foundation, before framing
As-built survey
- What it answers
- Where did the finished work actually end up?
- Typical timing
- After construction
These definitions follow how Fenstermaker and municipal handouts describe them. A location survey sits between a boundary survey and an as-built: it shows more detail than a boundary survey by documenting the improvements on the site. Names vary by city, so use your building department's term, not the one in your contract.
What a construction survey (staking) delivers
Staking, also called layout or setting out, gives the crew dimensional control through every stage of the work. For a building site, the surveyor typically provides:
- Building corner stakes. Monterey County's grading staking page calls for a minimum of four wooden stakes at the building corners, identified by purpose and compass orientation.
- Offset stakes. These sit a set distance from the true point so the marker survives excavation.
- Grade stakes. These show the finished or subgrade elevation at a point.
- Slope stakes. These mark where the ground meets a planned slope, which fixes the outer limit of cut or fill.
- Cut and fill marks. Cut is the top-of-hub elevation minus the design elevation; fill is the reverse. Crews write the offset distance, the cut or fill, and the point ID on the stake.
Who sets what is a contract question. One Alberta specification has the consultant provide baseline stakes and the contractor set final grade stakes. A county specification may leave extra horizontal and vertical control to the contractor. Read the Division 01 survey section of your specifications before the pre-construction meeting, because the answer decides who carries the cost of re-staking.
Expirations slip when nobody owns the date. Track filing and permit dates with reminders →
When your building department asks for a survey
There is no single national trigger. Three patterns show up in city and county handouts.
At permit application. A site plan is often required to be drawn from a boundary survey. The model-code language is in the site plan provision of the administration chapter (IBC 107.2.6 in recent editions, 107.2.5 in earlier ones). Berkeley's survey guidelines note that the California Building Code does not give clear guidance on when a boundary survey is required, so the city sets its own triggers, starting with how close the work is to the property line. Enid, Oklahoma, goes further: its code requires every site plan to include a boundary survey certified by a state-licensed land surveyor.
After footings or foundation. Some jurisdictions want proof the foundation is in the right place before you frame on top of it. In Alcoa, Tennessee, the foundation survey requirement says the survey goes to the building inspector within fifteen days of an approved footing inspection, and work stops after fifteen days until it arrives. Hilton Head Island, South Carolina, requires one when an addition is built within 2 feet of a setback or buffer line 20 feet away.
At close-out. Upper Mac requires a foundation as-built for all new residences showing the vertical and horizontal foundation location. Cutler Bay, Florida, asks for boundary and topographic surveys before closing out.
Some places accept a certification in place of a full survey. New Castle County, Delaware, accepts a foundation as-built certification from a licensed professional that location and elevation conform to the approved plans and no setback is encroached. Cupertino, California, can waive the licensed survey if the addition's setback is 10% greater than code requires.
Who has to do the survey
Boundary work is the clearest case: states license land surveyors, and building departments typically want a licensed surveyor's stamp. Alcoa requires that survey work be done by a registered land surveyor. Monterey County's inspection process verifies that proposed work was surveyed by a surveyor licensed by the State of California.
Construction staking is less uniform. Some state boards require a licensed surveyor or engineer in responsible charge of the primary control but do not license the staking itself, and others read their laws more strictly. The NCEES Model Law and Model Rules, which many boards start from, should be checked against your state's adopted version. If the rules are unclear, ask your state licensing board before you hire.
ALTA/NSPS surveys are a different animal
If a lender or buyer asks for an ALTA survey, that is a land title survey, not a construction survey. The 2021 ALTA/NSPS Minimum Standard Detail Requirements took effect February 23, 2021, and set the standard for surveys that title insurers rely on. They have eight sections plus an optional Table A list the client can request. State or local rules can add to the standard, and the stricter rule governs.
Do not substitute one for the other. A title survey will not stake your building, and staking data will not satisfy a title company.
A practical sequence for a typical building project
- Get a boundary and topographic survey first. Design from it. Many departments expect the site plan to match a boundary survey.
- Ask the building department for its survey checklist. Get the survey type, the timing (before footings, before framing, at final) and whether a stamped certificate is acceptable.
- Assign staking in the contract. Decide who sets control, building stakes and grade stakes, and who pays to replace them.
- Stake, then verify before you pour. Check the building corners against the plans, setbacks and the benchmark before footings go in.
- Order the foundation survey on a schedule. If your jurisdiction sets a deadline like Alcoa's fifteen days, book the surveyor before the footing inspection, not after.
- Keep the as-built. Record survey results in your document control system alongside the permit set so they are findable at close-out.
Deadlines like these differ by jurisdiction, so see how long a building permit is good for too. For fee and timing background see how much a building permit costs, and for city process pages see Los Angeles building permits.
Common questions
What is the difference between a boundary survey and a construction survey?
A boundary survey establishes property lines and legal boundaries using markers and measurements. A construction survey places the designed building, grades and utilities on the ground. You typically need the first to design and apply for the permit, and the second to build.
What is a foundation survey?
It checks that a poured foundation matches the design in both location and elevation. Many departments require one shortly after the footing or foundation inspection, and some accept a certification from a licensed professional instead.
Do I need a survey to get a building permit?
It depends on your building department. Some require a boundary survey with every application, some only when the work is close to a property line, and some waive it in narrow cases. Berkeley's guidelines say the California Building Code is not clear, so check your local checklist.
What is an as-built survey?
It records where finished elements actually ended up, and is done after the work is complete. It should not be confused with a foundation survey, which happens mid-project.
Is a construction survey the same as an ALTA survey?
No. An ALTA/NSPS survey is a land title survey for title insurance. A construction survey places new work. They answer different questions and are not interchangeable.
Does construction staking need a licensed surveyor?
It varies by state. Some boards require a licensed surveyor or engineer in charge of the control points but not for the staking itself; others are stricter. Check your state board.
Put every permit date on the calendar
Add the dates as tasks with an owner. Reminders go out 7 and 3 days before, the day before, and on the day.