IBC Construction Types: Type I-V Explained for Permits

Updated 7 min read

Short answer

The IBC defines five construction types, I through V, in Section 602. They are sorted by which building elements must be noncombustible, and Table 601 sets the fire-resistance ratings that separate the A and B subtypes.

Number of types
5 (I-V)
IBC 602
Where ratings live
Table 601
IBC 2018 and 2021 Chapter 6
Type IV in 2021
Mass timber IV-A, IV-B, IV-C and IV-HT
IBC 2021 602.4
On this page (7)
  1. What the five IBC construction types mean
  2. Types IA, IB, IIA and the rest: what the A and B subtypes mean
  3. What changed for Type IV in the 2021 IBC
  4. Why plan check cares about your construction type
  5. How to confirm your construction type for a real project
  6. Common mistakes with IBC construction types
  7. Common questions

The International Building Code (IBC) sorts every building into one of five construction types, Type I through Type V, in Section 602. The type depends on which building elements must be noncombustible and how many hours of fire resistance they need. Types I and II are noncombustible, Type III has noncombustible exterior walls, Type IV is heavy or mass timber, and Type V allows any material the code permits.

Plan reviewers check your construction type early because it drives so much else. The type you declare on the cover sheet limits what you can build and how big it can be. Declare it wrong and the correction comes back as a stack of comments on structure, fire ratings and area.

This guide covers what each type means, how the A and B subtypes differ, what changed for Type IV in the 2021 edition, and how to confirm the numbers for your jurisdiction.

What the five IBC construction types mean

Section 602 requires every building to be classified into one of the five types defined in Sections 602.2 through 602.5. Here is the plain-language version, based on the 2018 and 2021 editions of the code text.

TypeSectionWhat the code saysTypical shorthand
I602.2Building elements listed in Table 601 are noncombustible, with exceptions in Section 603Concrete and steel, highest fire resistance
II602.2Same noncombustible rule as Type I, with lower fire-resistance ratingsSteel or masonry, less protection
III602.3Exterior walls noncombustible; interior elements any material the code permits"Ordinary" construction
IV602.4Heavy timber in 2018; mass timber subtypes in 2021Heavy timber, mass timber
V602.5Structural elements, exterior walls and interior walls of any material the code permitsCommon wood frame

I

Section
602.2
What the code says
Building elements listed in Table 601 are noncombustible, with exceptions in Section 603
Typical shorthand
Concrete and steel, highest fire resistance

II

Section
602.2
What the code says
Same noncombustible rule as Type I, with lower fire-resistance ratings
Typical shorthand
Steel or masonry, less protection

III

Section
602.3
What the code says
Exterior walls noncombustible; interior elements any material the code permits
Typical shorthand
"Ordinary" construction

IV

Section
602.4
What the code says
Heavy timber in 2018; mass timber subtypes in 2021
Typical shorthand
Heavy timber, mass timber

V

Section
602.5
What the code says
Structural elements, exterior walls and interior walls of any material the code permits
Typical shorthand
Common wood frame

Two details matter here. The difference between Type I and Type II is not the material. Both require noncombustible elements. The difference is the fire-resistance ratings in Table 601. And "noncombustible" applies to the elements Table 601 lists, so a Type II building can still have some combustible items where Section 603 allows them.

The order also tracks fire performance. Type I is the most stringent and Type V has the fewest material requirements.

Types IA, IB, IIA and the rest: what the A and B subtypes mean

In the 2018 IBC, Types I, II, III and V are each split into an A and a B subtype. That gives you IA, IB, IIA, IIB, IIIA, IIIB, VA and VB. Type IV is shown as IV-HT in that edition.

The letter tells you the degree of fire resistance required for building elements and assemblies. A is the more protected version and B is the less protected one. A Type IIB building and a Type IIA building use the same family of noncombustible materials, but the IIA building needs more hours of rating on its structural frame, floors and roof.

Use this rule of thumb when you read a drawing set:

  1. The Roman numeral tells you the material family.
  2. The letter tells you how much protection that family gets.
  3. Table 601 gives you the actual hours, element by element.

Read the hours from the code edition your jurisdiction has adopted. The ratings and footnotes in Table 601 have changed between editions, and some cities publish their own amended version. We don't list hour values in this guide for that reason. Copying a number from a different edition is a common way to get a plan check comment.

Most delays start as a correction letter. See what the city will flag before you submit →

What changed for Type IV in the 2021 IBC

In the 2012 through 2018 editions, Type IV is heavy timber. Exterior walls are noncombustible, and interior elements are solid or laminated wood, heavy timber or structural composite lumber without concealed spaces.

The 2021 edition restructured the type. Section 602.4 now covers mass timber, with subtypes IV-A, IV-B, IV-C and IV-HT, and fire-resistance ratings that come from Table 601. Exterior walls can also use other materials permitted under 602.4.1 or 602.4.2, such as fire-retardant-treated wood or cross-laminated timber.

If your project involves mass timber, confirm which edition your jurisdiction enforces before you pick a subtype. A jurisdiction still on the 2018 IBC will not recognize IV-A, IV-B or IV-C. Check the 2021 Chapter 6 text from ICC against the 2018 text to see the difference side by side.

Why plan check cares about your construction type

The construction type limits allowable height, floor area and combustible materials. It also interacts with your occupancy classification, sprinkler status and fire separation distance. Reviewers read these together, so a mismatch anywhere shows up as a comment.

Here is how the type usually surfaces in review:

  • The cover sheet or code summary. The reviewer checks that the declared type matches the framing shown in your structural sheets. A Type IIB declaration with wood roof framing on the plans is a flag.
  • Fire-resistance rating notes. Rated walls, floors and the structural frame are checked against Table 601 for the declared type.
  • Area and height. The type is a column input to the height and area provisions, so an upgrade from VB to VA or from V to III can be how a design gets more floor area.
  • Material callouts. Combustible items in a noncombustible type must fit one of the exceptions in Section 603.

Section 602.1.1 also helps you. A building doesn't have to meet the details of a higher construction type than its occupancy requires, even if some of its features exceed that type. If you are designing to Type IIA but only need IIB, your reviewer can classify the building by the lower requirement.

For a worked view of what reviewers flag before you submit, see what plan check correction tracking covers. If a comment on construction type does land in your correction letter, respond to it with a matrix that points to the code section and the sheet you changed.

How to confirm your construction type for a real project

Follow these steps before you stamp the cover sheet.

  1. Find the adopted code edition. Your building department's website lists the IBC edition and local amendments in force.
  2. Identify the occupancy classification. The type has to satisfy the height and area limits for that occupancy.
  3. Pick the structural system. Concrete or steel frame points to Type I or II. Masonry exterior walls with wood interior framing points to Type III. Wood frame throughout points to Type V. Timber with large solid or laminated members points to Type IV.
  4. Read Section 602 for your edition. Match your system to the definition, not to a nickname.
  5. Read Table 601. Write down the rated hours for each element of your chosen subtype from the table in your adopted edition.
  6. Check local amendments. Some cities modify the subtypes or add their own. Search your jurisdiction's amendments for "Chapter 6" or "Table 601".
  7. State the type on the cover sheet. Include the section number and edition so the reviewer can follow your logic.

Common mistakes with IBC construction types

Treating "noncombustible" as one tier. Type I and Type II are both noncombustible. Choosing between them is about fire-resistance hours.

Using a table from the wrong edition. Table 601 values and footnotes differ across editions. Pull it from the code your department enforces.

Assuming Type IV means any timber building. Under 2018 rules, Type IV is a specific heavy-timber definition with no concealed spaces. Under 2021 rules, it is the mass timber family with its own subtypes.

Forgetting local adoption. Many states and cities adopt the IBC with amendments. The model-code section numbers here are a baseline. Your jurisdiction's amendments may differ; for a local example, see the Los Angeles building permits page.

Common questions

What is the difference between Type IIA and Type IIB construction?

Both use noncombustible building elements. The difference is the degree of fire resistance Table 601 requires. IIA is the more protected subtype and IIB is the less protected one.

What is Type V construction?

Type V is the type where structural elements, exterior walls and interior walls can be any material the code permits. It is the common wood-frame type, split into VA and VB by fire-resistance ratings.

What is Type III construction, and why is it called ordinary?

Type III has noncombustible exterior walls with interior elements of any material the code permits. Many sources call it ordinary construction, usually a masonry exterior with wood floors and roof.

Can I build with exposed heavy timber in Type IV?

Yes, where the edition and subtype allow it. In the 2018 IBC, Type IV interior elements are solid or laminated wood without concealed spaces. In the 2021 IBC, check the mass timber subtypes in Section 602.4. Confirm your jurisdiction's adopted edition first.

Where do I find the fire-resistance hours for my type?

Table 601 in your jurisdiction's adopted edition of the IBC. Exterior walls use a separate table: Table 602 in the 2015 and 2018 editions and Table 705.5 in the 2021 edition.

Does the construction type affect how long plan check takes?

Not directly, but a wrong or unclear type triggers corrections, and each correction round adds time. Declaring the type, section and edition on the cover sheet reduces those comments.