Mixed-Use Development
Ground-floor commercial with residential above, multi-phase permitting
Comprehensive project structure for mixed-use developments with ground-floor commercial and residential above. 9 phases including entitlements and closeout, 4 submittal packages covering building, grading, shoring, and fire sprinkler permits across 8 department tracks, and a full consultant team. Designed for design-build and architecture firms managing complex zoning overlays, multiple permit types, and 18-36 month timelines.
Project Phases
- 4%
Programming & Pre-Design
Site analysis, zoning research, market study, client program
- 12%
Entitlements & Approvals
Zoning applications, EIR, community engagement, planning commission
Follows: Programming & Pre-Design
- 10%
Schematic Design
Massing, unit mix, retail layout, parking structure, site plan
Follows: Entitlements & Approvals
- 16%
Design Development
Refined drawings, material selections, MEP coordination, structural system
Follows: Schematic Design
- 26%
Construction Documents
Permit-ready drawings, specifications, code compliance, consultant coordination
Follows: Design Development
- 14%
Permitting & Plan Check
Multi-department plan check, shoring permit, grading permit, corrections
Follows: Construction Documents
- 4%
Bidding & Negotiation
GC solicitation, bid leveling, contract negotiation, value engineering
Follows: Permitting & Plan Check
- 10%
Construction Administration
Submittals, RFIs, site visits, inspections, change orders
Follows: Bidding & Negotiation
- 4%
Project Closeout
Final inspections, certificate of occupancy, as-built drawings, warranty handoff
Follows: Construction Administration
Submittal Packages
Building Plan Check
buildingBuilding & SafetyFire PreventionPlanning & ZoningPublic Works / EngineeringUtility ConnectionsGrading Permit
gradingPublic Works / EngineeringShoring & Excavation Permit
buildingBuilding & SafetyFire Sprinkler Permit
fireFire Prevention
Suggested Consultants
Structural Engineer
structural
MEP Engineer
mep
Civil Engineer
civil
Landscape Architect
landscape
Geotechnical Engineer
geotechnical
Surveyor
surveyor
Environmental Consultant
environmental
Acoustical Consultant
acoustical
Document Structure
- 01-Design Documents
- 02-Specifications
- 03-Submittals & Permits
- 04-Correspondence
- 05-Meeting Notes
- 06-Site Photos
- 07-Reports & Studies
- 08-Entitlements & Zoning
- 09-Environmental
- 10-Cost Estimates
Jurisdiction Profile
Estimated review timeline: 60 days
Mixed-use projects often require concurrent submittals across multiple departments. Entitlements can add 6-12 months. Shoring permits may be required before building permit.
Free 14-day trial. No credit card required.
More templates
Single-Family Residential
A ready-to-use project structure for residential architecture projects. Includes 7 design phases with duration ratios...
RFI Tracker for Architecture & Engineering Teams
A comprehensive RFI tracking template designed specifically for architecture and engineering firms managing the desig...
Multi-Family Residential
Project structure for multi-unit residential developments with complex entitlements and multi-department submittals....