As-Built Drawings: What They Are and When Cities Want Them

Updated 8 min read

Short answer

As-built drawings show the project as it was actually constructed, including every field change. The contractor marks them up during construction. Some cities require them before a certificate of occupancy; others only when the work departed from the approved plans.

Durham, NC as-built timing
Approved as-builts required before water meter and sewer connections and before the certificate of occupancy
City of Durham, As-Built Drawings page
Alabama state spec 01 78 39
Three red-lined record drawing sets at final inspection, plus PDF copies
Alabama State Building Commission, Section 01 78 39
Kennewick, WA record drawings
Submitted as PDF and TIFF; a conditional CO may issue while they are pending
City of Kennewick, Commercial CO and Final Inspection packet
On this page (8)
  1. What are as-built drawings?
  2. As-built drawings vs record drawings
  3. Who makes as-built drawings?
  4. When does a building department require as-built drawings?
  5. As-builts are not a substitute for amended plans
  6. How to keep as-built drawings accurate
  7. What to include on as-built drawings
  8. Common questions

As-built drawings are the drawings that show how a building was actually constructed, with every field change, relocated fixture and substituted material marked on them. The contractor keeps the marked-up set during construction and hands it over at closeout. Whether a city building department asks for them depends on the jurisdiction and on whether the work departed from the permitted plans.

Most of the confusion around the term comes from two places. The word "as-built" means slightly different things in different contracts, and the building department, the owner and the architect each want a different version of the same information. This guide sorts out which is which.

What are as-built drawings?

As-built drawings are the final record of the project as constructed, as opposed to as designed. They capture what changed between the permit set and the finished building: dimensions, locations, materials, and anything the crew adjusted for unforeseen site conditions, design changes or owner requests. Construction drawings show design intent. As-builts record the result.

You will also hear them called record drawings or red-line drawings. Those names overlap but are not always interchangeable, as the next section explains. What every version has in common is the purpose. Owners need them later for renovations, maintenance, a sale, or eventual demolition, and many closeout packages treat them as a required deliverable before final payment.

As-built drawings vs record drawings

The sources disagree on the definitions, so the contract on your project controls. There are two common usages.

Usage A (AIA-style practice)Usage B (field-verification practice)
As-builtThe contractor's red-ink markups on a working setMeasured, verified conditions of the finished work
Record drawingsThe formal set the architect or engineer produces from the markupsRevised design documents
Who prepares themContractor marks up; design team drafts the final setOften a surveyor or scanning firm
How reliableOnly as accurate as the contractor's markupsAs accurate as the field verification

As-built

Usage A (AIA-style practice)
The contractor's red-ink markups on a working set
Usage B (field-verification practice)
Measured, verified conditions of the finished work

Record drawings

Usage A (AIA-style practice)
The formal set the architect or engineer produces from the markups
Usage B (field-verification practice)
Revised design documents

Who prepares them

Usage A (AIA-style practice)
Contractor marks up; design team drafts the final set
Usage B (field-verification practice)
Often a surveyor or scanning firm

How reliable

Usage A (AIA-style practice)
Only as accurate as the contractor's markups
Usage B (field-verification practice)
As accurate as the field verification

Under AIA documents, the term "as-built" does not appear in the A201 contract. According to AIA's own contract commentary, A201-2017 section 3.11 requires the contractor to maintain an updated set of documents as a record of the work as constructed. Under the B101 owner-architect agreement, as-constructed record drawings are a supplemental architect service, and the architect is not responsible for the accuracy of the contractor's information they are based on. Those are paraphrases from a secondary source, so read the exact wording in your own contract form.

The practical advice is simple. On kickoff, find out which document your project calls what, who owes it, and in what format (PDF redlines, CAD or BIM).

Consultants, files and deadlines in one place. Run this project in Olumba →

Who makes as-built drawings?

On most projects the split looks like this:

  1. The contractor keeps a clean set of the contract drawings and marks every change as it happens. Model closeout specifications say to record changes as they occur and not to wait until the end of the project.
  2. Subcontractors mark up their own trades, such as underground utilities, mechanical, electrical and fire protection. The general contractor collects and coordinates them.
  3. The design team may convert the redlines into a formal record set, if the owner-architect agreement includes that service. The University of Southern California's closeout checklist, for example, splits it this way: the contractor supplies as-builts and the architect or engineer prepares the final record drawings.
  4. A surveyor or scanning firm may verify underground and concealed conditions, especially where the owner wants measured accuracy.

The record set is kept separate from the working construction documents. One version of CSI Section 01 78 39, the standard project-record-documents section, states that record documents must not be used for construction purposes. Keeping them apart prevents the crew from building off an incomplete markup.

When does a building department require as-built drawings?

There is no single national rule. What the sources show is a pattern: some departments tie as-builts to the final inspection or certificate of occupancy, and others only ask for them when the work deviated from the approved plans.

JurisdictionWhat it asks forWhen
Danbury, CTFinal revised as-built drawings, among other closeout paperworkBefore an occupancy certificate is granted
West Palm Beach, FLAs-builts approved by the cityBefore the CO
Fort Myers, FLA final as-built approved by the Engineering Division in Public WorksAfter the building final passes, as a CO condition
Kennewick, WARecord drawings as PDF and TIFF files, reviewed by Public WorksA conditional CO may issue while they are pending
Cherry Hills Village, CODrainage certification, a stamped engineer letter with as-built drawingsOn the minimum list for a CO
Durham, NCApproved as-builts on 24" x 36" sheets, corrected to the as-built conditionBefore water meter and sewer connections and before the CO

Danbury, CT

What it asks for
Final revised as-built drawings, among other closeout paperwork
When
Before an occupancy certificate is granted

West Palm Beach, FL

What it asks for
As-builts approved by the city
When
Before the CO

Fort Myers, FL

What it asks for
A final as-built approved by the Engineering Division in Public Works
When
After the building final passes, as a CO condition

Kennewick, WA

What it asks for
Record drawings as PDF and TIFF files, reviewed by Public Works
When
A conditional CO may issue while they are pending

Cherry Hills Village, CO

What it asks for
Drainage certification, a stamped engineer letter with as-built drawings
When
On the minimum list for a CO

Durham, NC

What it asks for
Approved as-builts on 24" x 36" sheets, corrected to the as-built condition
When
Before water meter and sewer connections and before the CO

Two things stand out. First, many of the as-built requirements are tied to site work such as drainage, utilities and engineering sign-off, not to the building interior. Second, the order differs. Danbury and Durham want the drawings before occupancy. A Berkeley facilities FAQ lists as-builts as a closeout item after the final inspection passes. Confirm the sequence with your own building department before you promise a date to the owner.

A third-party consultant's guide reports that when field work departs from the approved plans, the department usually expects a corrective step, such as revised plans or a revision application, and recommends contacting the department before the final inspection. That is a vendor source, so treat it as a prompt to ask the building department rather than as a rule.

As-builts are not a substitute for amended plans

This is the trap. If you change the work in a way that no longer matches the approved construction documents, you generally can't just note it on the as-builts at the end.

The model code addresses this directly. IBC section 107.4, "Amended construction documents," says work is to be installed in accordance with the approved construction documents, and changes made during construction that do not comply with them must be resubmitted for approval as an amended set. The text is on the ICC's 2012 IBC chapter 1, and the requirement is consistent across the editions I could find. Jurisdictions amend it. Massachusetts, for example, requires the amended set to be submitted before the proposed work begins.

One practitioner thread argues that 107.4 does not require every field change to be submitted, only changes that don't comply with the approved documents. That is an individual reading, not an official interpretation. The safe workflow:

  1. Code-relevant change? (Egress, fire-resistance, structural, accessibility, energy.) Submit a revision to the building department and get it approved before you build it.
  2. Minor field adjustment that still complies? Record it on the as-builts. Mention it to your inspector if you're unsure.
  3. Unsure? Ask the plan reviewer or inspector, and keep their answer in writing.

If the building department also needs to approve revisions, track them like correction items so the approval is on file before final. The plan check correction tracking guide covers how to keep that list.

How to keep as-built drawings accurate

Accuracy is the whole point, and it is the part that fails most often. A record set is only as good as the field notes behind it.

  1. Start on day one. Dedicate a clean, current set as the as-built set and designate one person responsible for it.
  2. Mark changes the same day. The Alabama state version of the record-documents section asks for changes to be recorded as they occur.
  3. Reference the paper trail. Next to each markup, note the RFI number, change order or bulletin that caused it. A reviewer can then trace it. For the difference between the two, see RFI vs submittal, and for how change orders get written, see how to write a change order.
  4. Photograph concealed work before it's covered. Underground lines, in-wall plumbing and above-ceiling runs are the hardest to reconstruct afterward.
  5. Review the set at punch list. The Alabama section asks for a red-lined set at the punch-list inspection so deficiencies can be fixed before final inspection.
  6. Check against the closeout spec. Count the sets, confirm the format and note any sealing or signature requirement. The Alabama version of the section asks for three marked-up record drawing sets at final inspection, plus electronic PDF copies. Other owners ask for one set, or for the markups to go into the O&M manuals.

What to include on as-built drawings

A usable set shows, at minimum:

  • Final dimensions and locations of walls, openings and equipment where they differ from the plans
  • Routing of concealed utilities, with depths or elevations for underground work
  • Substituted materials and products, and the approved submittal they came from
  • Revisions that came from RFIs, change orders, field directives and addenda
  • Updated schedules, such as door, window and panel schedules, when they changed
  • Required signatures or seals, where the owner or jurisdiction asks for them

A vendor guide lists the typical contents as final floor plans, site plan updates, structural details and MEP layouts. Your closeout spec will list what your project needs.

Common questions

Are as-built drawings required by code?

Not as a general rule. The model building code requires that changes from the approved plans be resubmitted as amended construction documents (IBC 107.4). Requirements for as-built drawings as such come from the local building department, a public works or engineering division, or the owner's contract, so check the department's final inspection or CO checklist.

Who pays for as-built drawings?

It depends on the contract. The contractor's field markups are usually part of the contractor's scope. If the owner wants the architect to produce formal record drawings from them, that is typically a separate service under the owner-architect agreement, which the AIA B101 lists as a supplemental service.

Are as-built drawings the same as record drawings?

Sometimes. In AIA-style practice, as-builts are the contractor's markups and record drawings are the formal set produced from them. In survey practice, "as-built" means verified field conditions. Use the definition in your contract and ask if it isn't stated.

What happens if there are no as-built drawings at closeout?

On many commercial projects the closeout package includes them before final payment is released, so their absence can hold up payment. In jurisdictions that tie them to the certificate of occupancy, it can hold up occupancy too. Kennewick, WA is one example where a conditional CO can issue while record drawings are still pending.

Can you create as-built drawings after construction is finished?

Yes. Surveyors and scanning firms measure the finished building and draft a set. It costs more and cannot see inside closed walls, which is why recording concealed work during construction is cheaper and more accurate.

If you're collecting redlines, RFIs and revisions across subs, a single project record keeps the paper trail attached to each change. That is the job Olumba projects are built for. For the other half of closeout, see construction document control.

Get permit notes like this by email

Practical notes from real plan-check cycles: what reviewers flag and how to get ahead of it. A few emails a month.