How to Write a Change Order: Contents and Steps
Updated 7 min read
Short answer
A change order is a written agreement that changes the scope, the contract sum and the contract time. Describe the work precisely, price it, state the days added or removed, and get the owner, contractor and architect to sign before work starts.
- Who signs a change order
- Owner, contractor and architect
- AIA A201 Section 7.2
- Standard AIA change order form
- G701
- AIA Contract Documents
- Standard AIA change directive form
- G714
- AIA Contract Documents
On this page (8)
To write a change order, state in writing what work is being added, removed or altered, what that does to the contract sum, and what it does to the contract time. Then get every party the contract names to sign it before the changed work starts. On an AIA-style contract that means the owner, the contractor and the architect.
Everything else in this guide is detail on those four pieces: the description, the price, the time and the signatures. It is written for project managers, architects and contractors who have to produce one under deadline pressure, usually with the work already half in motion.
Start with the contract, not a template
Your contract decides who can issue a change order, who must approve it, how it is priced and how fast notice has to be given. A generic template does not override any of that. The guides that rank for this topic agree on this point: check the contract's change clause first, because it usually names who submits change orders and how they are approved. If the contract names no form, a contractor can draft one as long as the key information is present.
On projects using AIA A201, Article 7 allows three ways to change the work after the contract is signed: a change order, a construction change directive, or an order for a minor change. Section 7.1.1 says changes are made through one of those three, subject to the limits in Article 7. Which one you need depends on whether the parties already agree on price and time.
| Tool | Use it when | Who signs | AIA form |
|---|---|---|---|
| Change order | Everyone agrees on the scope, the price and the time | Owner, contractor and architect | G701 |
| Construction change directive | The owner wants the work done now and price or time is still open | Owner and architect | G714 |
| Order for a minor change | The change affects neither cost nor time | Architect | Often an architect's supplemental instruction |
Change order
- Use it when
- Everyone agrees on the scope, the price and the time
- Who signs
- Owner, contractor and architect
- AIA form
- G701
Construction change directive
- Use it when
- The owner wants the work done now and price or time is still open
- Who signs
- Owner and architect
- AIA form
- G714
Order for a minor change
- Use it when
- The change affects neither cost nor time
- Who signs
- Architect
- AIA form
- Often an architect's supplemental instruction
The AIA's own guidance describes change orders as documented on G701 and effective once all three parties sign, and a change directive as the written order used when there is no full agreement on the terms. Secondary sources differ on exactly who signs a directive. Check the signature block in your own contract documents instead of relying on a summary, including this one.
What a change order must say
A change order is a short document. It does one job: record an agreement that changes the contract. These are the parts it needs.
- Project and contract identification. Project name, the contract it amends, the change order number, and the date.
- A description of the change. This is the part that causes most disputes. Write it in full sentences with specifics, so that nobody can read it two ways. Name the drawing sheets, detail numbers or specification sections that change, and say whether the work is added, deleted or substituted. "Revise stair 2 per RFI 41" is weaker than "Replace the 3-inch concrete-filled pan treads at stair 2, levels 1 to 3, with the precast treads shown in sketch SK-12."
- The reason. Owner request, unforeseen condition, design correction, or code requirement. You don't need an essay. One line makes the later audit trail readable.
- The price. The adjustment to the contract sum, with the original sum, the sum before this change, and the new sum.
- The time. The adjustment to the contract time in days, and the resulting date for substantial completion. If the change adds no time, say "0 days" instead of leaving the line blank. Time extensions can matter as much as the money, so don't skip this.
- Signatures and dates. Every party the contract requires.
The AIA's framing is the useful one here: a change order adjusts the scope of the work, the contract sum and the contract time in a single written instrument. If your draft is missing one of the three, it isn't finished.
Consultants, files and deadlines in one place. Run this project in Olumba →
How to price the change
Price the change in the way your contract says. Contracts usually offer a short list: a lump sum, unit prices already in the contract, or cost plus a fee. If the contract is silent, agree on the method in writing before anyone builds up numbers.
A clean breakdown lets the owner and architect check your arithmetic, which is what gets a change order approved quickly. Break it down like this:
- Direct costs first. Labor (hours times the burdened rate), materials, equipment, and the cost of any subcontractor's own change order.
- Then markups, in the order the contract states. Overhead, profit and bond cost are applied to the direct cost sequentially or as a single combined percentage, depending on the contract. Don't add overhead twice when a combined markup already includes it.
- Deducts count too. If the change removes work, price the credit with the same level of detail. The AIA publishes guidance on contractor overhead and profit for deductive and net-increase change orders. For a net increase, overhead and profit can be added based on the net increase in the contract sum.
Industry blogs often quote a typical percentage for overhead and profit. Treat those numbers as illustrative. The contract's percentage governs, and where the contract is silent, use one consistent, documented method instead of borrowing someone else's rate.
Attach backup: subcontractor quotes, supplier quotes, and a labor sheet. The owner's side will ask for them, so send them with the first submission and save a round trip.
How to state the schedule impact
Don't write "time extension to be determined" and move on. Either quantify it or reserve it explicitly. Say how many calendar days are added, and give the new substantial completion date. If the change might affect the critical path but you can't yet say how much, say so in the change order and state what you are reserving.
Contracts differ on how time claims are waived or preserved once a change order is signed, so read that clause before you sign one that is silent on time.
When a change directive is the better tool
Sometimes the work can't wait for agreement. The owner needs the wall moved this week, and the price is not settled. That is what a construction change directive is for. Under A201 Section 7.3, a directive is a written order that tells the contractor to proceed with a change before the parties have agreed on any adjustment to the contract sum or time. Sources describing the 2017 form generally say the contractor must proceed promptly with the directed work even while the cost is disputed, and that a disagreement over the time adjustment can become a claim under Article 15. Verify the exact section numbers against your copy of the A201.
Use a change order when you can agree first. Use a directive when you can't. Afterward, the final price and time from a directive are normally folded into a change order so the contract sum reflects them.
Where change orders come from
Change orders rarely start as change orders. They start somewhere else in the project record, and your paper trail should show that origin.
- An RFI. A question exposes a conflict or an omission in the documents, and the answer changes the work. See RFI vs submittal for how the two logs differ.
- A submittal. A substituted product changes cost or time, and the architect accepts it.
- A field condition. Something under the slab or behind the wall is not what the drawings showed.
- A code or plan-check comment. A reviewer asks for something the permit set did not include. See how to respond to a plan check correction letter.
- An owner request. The simplest source and usually the cleanest.
Cite the source document by number in the change order description. When the RFI log, the submittal log and the change order log all reference each other, an auditor or a lender can follow the thread without calling you.
A short drafting checklist
- Read the contract's change clause for who, how and how fast.
- Write the description with sheet, detail and spec references.
- Price it using the contract's method, with direct costs, then markups.
- State days added or removed and the new completion date.
- Attach sub and supplier quotes.
- Send it to everyone who must sign, and log the date sent.
- Don't start the changed work until it's signed, unless a directive says otherwise.
Starting before signature is the usual way payment disputes begin, so get the go-ahead in writing.
Common questions
What is the difference between a change order and a change directive?
A change order records an agreement on scope, price and time, signed by the owner, contractor and architect on an AIA contract. A construction change directive is an order to proceed with a change before price or time is agreed. Use the directive when the work can't wait.
Who has to sign a change order?
It depends on your contract. Under AIA A201 Section 7.2, the owner, the contractor and the architect sign. Other contract forms may name different parties, so check the change clause in yours.
Can a contractor write a change order?
Yes. If the contract does not name a specific form, a contractor can draft one as long as it includes the description, price, time and signature blocks. Ask who drafts it on your project.
Do I need a change order if the cost doesn't change?
If a change affects neither cost nor time, A201 Article 7 allows an order for a minor change instead. If it touches either one, use a change order or a directive.
What happens if I do the work before the change order is signed?
You may have trouble getting paid for it. The contract's notice and change provisions control, so read them before proceeding. If the owner wants the work started immediately, ask for a construction change directive in writing.
Get permit notes like this by email
Practical notes from real plan-check cycles: what reviewers flag and how to get ahead of it. A few emails a month.
Unsubscribe anytime from any email.
Run your permits and projects in one place
Tasks, files, consultants and permit dates, with reminders that go out on their own.