RFI vs Submittal: What's the Difference in Construction?

Updated 8 min read

Short answer

An RFI asks the design team a question about the contract documents. A submittal asks the design team to review a specific product, drawing or sample for conformance. An RFI gets an answer; a submittal gets an action stamp.

Submittals are contract documents?
No
AIA A201 Section 3.12.4
Reporting a discrepancy in the documents
Promptly, as an RFI
AIA A201 Section 3.2.1
One owner's internal RFI turnaround
5 working days
NTTA CON-01 (ntta.org)
On this page (9)
  1. RFI vs submittal at a glance
  2. What is an RFI in construction?
  3. What is a submittal in construction?
  4. Where the line blurs
  5. What each one costs you in schedule
  6. How to write an RFI that gets a fast answer
  7. How to prepare a submittal that doesn't bounce
  8. Keeping both logs straight
  9. Common questions

An RFI (request for information) asks the design team a question about the contract documents. A submittal asks the design team to review a specific product, drawing or sample to confirm it meets the contract documents. The RFI gets an answer. The submittal gets a review action. They run on separate logs with separate clocks, and mixing them up is how a simple approval ends up stuck in the wrong queue.

This guide covers where each one comes from, who sends it, what comes back, and what to do when something could be either. It is written for project managers, architects and engineers who handle both every week.

RFI vs submittal at a glance

RFISubmittal
What it isA written questionA package for review
Triggered bySomething unclear, missing or conflicting in the drawings or specs, or a field condition nobody anticipatedA spec section that requires a product, shop drawing, sample or certificate to be reviewed
Who starts itUsually the contractor, but any party can askThe contractor, from its subs and suppliers
Who answersThe architect or engineer of record, sometimes with consultantsThe architect or engineer, per the spec's review process
What comes backA written answer, sometimes with a sketch or a revised detailAn action: approved, approved as noted, revise and resubmit, or rejected (your spec sets the exact terms)
Where the list livesRFI logSubmittal log
Does the answer change the contract?Not by itself. A change needs a separate instrumentNo. Review does not amend the contract

What it is

RFI
A written question
Submittal
A package for review

Triggered by

RFI
Something unclear, missing or conflicting in the drawings or specs, or a field condition nobody anticipated
Submittal
A spec section that requires a product, shop drawing, sample or certificate to be reviewed

Who starts it

RFI
Usually the contractor, but any party can ask
Submittal
The contractor, from its subs and suppliers

Who answers

RFI
The architect or engineer of record, sometimes with consultants
Submittal
The architect or engineer, per the spec's review process

What comes back

RFI
A written answer, sometimes with a sketch or a revised detail
Submittal
An action: approved, approved as noted, revise and resubmit, or rejected (your spec sets the exact terms)

Where the list lives

RFI
RFI log
Submittal
Submittal log

Does the answer change the contract?

RFI
Not by itself. A change needs a separate instrument
Submittal
No. Review does not amend the contract

The one-line test: if you are asking "what do you want here?" it is an RFI. If you are saying "here is what we plan to put here, is it OK?" it is a submittal.

What is an RFI in construction?

An RFI is a formal written request for an interpretation of the contract documents or for more information needed to build the work. The AIA publishes a standard form for it, G716 (the 2004 edition is documented on AIA Contract Documents' help site, and a newer F706-2024 form is also listed there).

The AIA A201 general conditions tie the RFI to one specific duty. Section 3.2.1 tells the contractor to report errors, inconsistencies or omissions it discovers in the contract documents promptly to the architect as a request for information, according to the secondary sources reviewed for this guide. Check the exact wording in the edition of the A201 your contract incorporates.

Typical RFI triggers:

  • A dimension on the architectural plan doesn't match the structural plan.
  • A spec calls for a product that is no longer made.
  • The drawings are silent on how two assemblies meet.
  • Existing conditions behind a wall differ from what the drawings show.

An RFI is not a place to ask for permission to substitute a product, and it is not a place to ask for a time extension. Those have their own routes.

Consultants, files and deadlines in one place. Run this project in Olumba →

What is a submittal in construction?

A submittal is material the contractor sends to the design team so they can check it against the contract documents before the work is built or ordered. The A201 names three main kinds: shop drawings, product data and samples. Specs often add mockups, certificates, test reports and closeout items.

Two A201 provisions matter most in practice:

  • Section 3.12.4: shop drawings, product data, samples and similar submittals are not contract documents. Their purpose is to show how the contractor plans to meet the design intent.
  • Section 3.12.7: the contractor does not start the related work until the architect has approved the submittal.

Section numbers for the contractor's representations about its own review differ between sources (some say 3.12.5, others 3.12.6), so confirm against your edition. The principle is stable: the contractor reviews a submittal before sending it on, and the architect's approval doesn't excuse the contractor from deviations it didn't flag in writing.

For the spec side, a Division 01 section titled Submittal Procedures (01 33 00 in the CSI format) usually sets out how many copies, how transmittals are numbered, and how long review takes. The federal UFGS 01 33 00 is a public example. For how to build the tracking sheet, see the construction submittal log template.

Where the line blurs

Most mix-ups happen in a handful of situations.

You already know the product and want it approved

Send a submittal. One summary of the industry sources notes that routing a plain approval through the RFI process adds steps and delay. The spec said what to submit. Submit it.

The spec requires a submittal, but the spec itself is unclear

Do both, in order. Send an RFI to resolve what the spec means, then send the submittal that reflects the answer. Put the RFI number in the submittal's notes so the reviewer can see the link.

The submittal shows a deviation

A201 Section 3.12.8, as summarized in the sources reviewed, says the architect's approval doesn't relieve the contractor of responsibility for deviations unless the contractor specifically flagged them in writing at submittal. Flag the deviation in the transmittal itself. Don't bury it in a drawing note, and don't assume an RFI response covers it unless the response says so.

You want to substitute a product

That is neither a plain RFI nor a plain submittal. Most specs have a substitution request procedure, often in Division 01. Follow it.

A field condition affects a product you've already submitted

Send an RFI to ask how the design should adapt, then revise and resubmit the product once you have the answer.

What each one costs you in schedule

Both consume time, and both belong on the schedule.

For submittals, the review period is set by your spec or contract. Back-schedule from the date the material must be on site: fabrication, then review, then the time to prepare the package.

For RFIs, the A201 uses a "reasonable promptness" standard for the architect's response, as summarized by commentators, and parties often agree specific response times instead. Industry guidance commonly cites a window of days, but the number comes from the contract, so read yours. Public owners publish their own procedures. The North Texas Tollway Authority's CON-01 procedure says a designee who can answer an RFI alone should send the final response to the contractor within a maximum of 5 working days of receipt. Treat that as one owner's internal target, not an industry rule.

An RFI answer does not automatically entitle you to more money or time. New Jersey DOT's RFI form carries a disclaimer that the RFI response does not entitle the contractor to additional time or an increase in price. If you believe the answer changes cost or schedule, say so in writing right away and follow the change procedure in your contract. Some specs set a notice window, so don't wait.

How to write an RFI that gets a fast answer

Reviewers answer short, specific questions first. NTTA's procedure says contractors should give enough background detail to make the question clear, and that incomplete questions can be sent back.

  1. One question per RFI. Two questions mean two answers and two chances to stall.
  2. Cite the documents. Give the sheet number, detail number and spec section.
  3. State your proposed solution. "We propose to do X. Please confirm." gives the reviewer something to approve.
  4. Attach a marked-up sketch or photo of the condition.
  5. Give the date you need the answer and what depends on it.
  6. Say whether you think it affects cost or time. Don't leave that to the response.

How to prepare a submittal that doesn't bounce

  1. Start from the spec section. List what it requires. Missing items are the top cause of returns.
  2. Check it yourself first. The contractor's review comes before the architect's.
  3. Mark the exact product, options and finishes on catalog sheets. A 40-page cut sheet with nothing circled invites a rejection.
  4. Submit related items together where the spec allows, so the reviewer sees the whole assembly.
  5. Flag deviations in the transmittal.
  6. Track it on the log with the date sent, the date due back and the resubmittal number.

Keeping both logs straight

The two logs should talk to each other. Link any RFI that touches a submitted product, and any submittal that waits on an RFI answer. When a reviewer returns a submittal "revise and resubmit," check whether the comment is really a question. If it is, that is an RFI waiting to be written.

Teams that keep these in separate spreadsheets lose the connection. Whatever tool you use, keep a single numbering scheme and a record of who sent what and when. The construction document control guide covers the broader practice, and the FAQ covers common questions about tracking project documents.

Common questions

Is an RFI the same as a submittal?

No. An RFI asks a question about the contract documents and gets a written answer. A submittal sends a product, drawing or sample for review and gets an action. They have separate logs and separate review clocks.

Can you use an RFI to get a submittal approved?

Not as a rule. If the spec requires a submittal, the approval comes through the submittal process. An RFI can resolve an unclear spec first, but it doesn't replace the review. Check your contract and Division 01 for the governing procedure.

Are submittals part of the contract documents?

Under AIA A201 Section 3.12.4, shop drawings, product data, samples and similar submittals are not contract documents. Review of a submittal doesn't amend the contract.

Who answers an RFI?

The architect or engineer of record, usually with input from consultants. On public projects the owner's own procedure may route the question to a designee or subject matter expert first, as NTTA's does.

How long does an RFI response take?

It depends on the contract. The A201 uses a "reasonable promptness" standard, and many contracts set a specific number of days. Read your general conditions and Division 01 for the real figure.

Does an RFI response change the contract price or schedule?

Not by itself. If you think it does, notify the architect and owner in writing promptly and follow the change process in your contract.

Get permit notes like this by email

Practical notes from real plan-check cycles: what reviewers flag and how to get ahead of it. A few emails a month.

Unsubscribe anytime from any email.

Run your permits and projects in one place

Tasks, files, consultants and permit dates, with reminders that go out on their own.

Start free