Deferred Submittal for a Building Permit: How It Works
Updated 8 min read
Short answer
A deferred submittal is a part of the design left out of the permit application and filed after the permit is issued. The building official must approve the deferral first, and the work can't be installed until that package is approved.
- Building official approval before deferring
- Required
- IBC 107.3.4.1 (as cited by Utah DFCM guidelines)
- First review of a deferred fire sprinkler package
- About 2 weeks
- City of Newport Beach
- Deferred fire sprinkler submittals in San Diego
- Not allowed from Jan 1, 2020
- City of San Diego notice
On this page (9)
- What is a deferred submittal?
- Do you need the building official's approval to defer?
- What can be deferred?
- What has to be on the plans at permit application?
- How do you file a deferred submittal after the permit is issued?
- When can the deferred work start?
- Deferred submittal vs. plan check correction vs. revision
- Mistakes that cost time
- Common questions
A deferred submittal is a portion of the design that you leave out of the original building permit application and submit to the building department later, after the permit is issued. The building official has to agree to the deferral before you file, the design professional in responsible charge has to review the package before it goes in, and the work it covers can't be installed until the department approves it.
That is the rule in plain terms. The details that trip people up are which items qualify, what goes on the plans at application, and which approval gates the inspection schedule. This guide covers those. It is written for architects, engineers and permit expediters who have to get a permit out the door without holding it for a sprinkler shop drawing.
What is a deferred submittal?
Menlo Park, California describes deferred submittals as a portion of a construction design not included in the initial building permit application and submitted after permit issuance for review and approval. Maricopa County describes the same idea as portions of a complete design that are not submitted at the time of application and are to be submitted to the building official within a specified period.
The usual reason is that a specialty contractor or manufacturer designs the item, and that firm isn't hired until after permit issuance. Fire sprinkler layouts and prefabricated trusses are the standard examples. The engineer of record shows the system on the permit set and defers the engineered detail.
Note: Some sources place the definition in Section 202 of the model code and others in a subsection of 107. Numbering also shifts between code editions. Check the edition your jurisdiction has adopted before you quote a section number on a drawing.
Do you need the building official's approval to defer?
Yes. The model code requires it. The Utah DFCM deferred submittal guidelines cite IBC 107.3.4.1 for the building official's approval of deferred submittals, and note that the official is not required to allow them. Tracy, California says the same in its bulletin: deferrals of any submittal items shall have prior approval of the Building Official.
Some departments go further and restrict the practice:
- Newport Beach's older notice requires sprinkler and alarm drawings with the initial submittal for new commercial construction and multi-dwelling units, unless the Building Director and Fire Marshal approve a deferral.
So the first step is never "draft the package." It is "find out whether this department lets you defer that item at all."
Expirations slip when nobody owns the date. Track filing and permit dates with reminders →
What can be deferred?
There is no single national list. Local departments publish their own. The common items that show up across city and county checklists:
| Category | Typical deferred items | Example source |
|---|---|---|
| Structural | Prefabricated roof and floor trusses | Kyle, TX checklist |
| Architectural | Storefront and curtain wall systems, exterior envelope items | Kyle, TX checklist; San Diego IB 188 |
| Fire protection | Fire sprinkler plans, fire alarm | Newport Beach; San Diego IB 188 |
| Vertical transportation | Elevator support rail | San Diego IB 188 |
Structural
- Typical deferred items
- Prefabricated roof and floor trusses
- Example source
- Kyle, TX checklist
Architectural
- Typical deferred items
- Storefront and curtain wall systems, exterior envelope items
- Example source
- Kyle, TX checklist; San Diego IB 188
Fire protection
- Typical deferred items
- Fire sprinkler plans, fire alarm
- Example source
- Newport Beach; San Diego IB 188
Vertical transportation
- Typical deferred items
- Elevator support rail
- Example source
- San Diego IB 188
Utah's state construction office is stricter than most. Its policy does not allow delegated design beyond the five named exceptions on its deferred submittal list.
If your item isn't on the local list, ask before you assume it can be deferred. A reviewer who sees an unlisted item on the deferred list may send it back as a plan check correction instead.
What has to be on the plans at permit application?
Most departments want the deferral declared up front. Menlo Park says deferred submittal items must be listed on the plans by the design professional in responsible charge at the time of building permit application. Rancho Cordova's policy has the same step: the registered design professional in responsible charge lists the deferred submittals on the construction documents for review by the building official.
A practical checklist for the permit set:
- Add a "Deferred submittals" list to the cover sheet or code sheet, one line per item.
- Show the item's location, loads and interfaces on the base drawings, so the specialty designer has something to design to.
- Fill in the department's deferred submittal form or agreement if it has one. Several do, including Bend and Wilsonville.
- Confirm in writing which agency reviews it. In some places the fire marshal reviews sprinkler deferrals, as Santa Fe's fire marshal's office does.
How do you file a deferred submittal after the permit is issued?
The sequence is the same in most departments, even though forms and portals differ.
- The specialty designer prepares the package. A vendor guide describes it as stamped, sealed, and complete to the standard of an independent permit submittal for that system.
- The design professional in responsible charge reviews it first. Wilsonville says each deferred submittal must be reviewed and approved by the design professional in responsible charge prior to submitting to the Building Division. Lynnwood says items that haven't been reviewed by the design professional in responsible charge will not be accepted. Portland says reviewers add a notation to the deferred drawings showing general conformance with the building design.
- You file with the building department. Use the department's deferred submittal form or portal record type. Some use one combined form for deferred submittals and revisions, such as Laguna Hills' plan check revision or deferred submittal application.
- The department reviews and approves it. Newport Beach asks you to allow an average of 2 weeks for the first review of fire sprinkler, fire alarm and truss deferrals. Other departments publish different turnarounds, so check yours.
- You install only after approval. See the next section.
When can the deferred work start?
Not before approval. Bend's agreement says the items shall not be installed until the design and submittal items have been approved by the Building Safety Division. Tracy's bulletin says the same. Wilsonville goes further and treats work done before approval as work performed without a permit.
Approval also has to land before a specific inspection in some places. Auburn, California's application says a deferred sprinkler plan must be submitted, reviewed, approved and available onsite at the time of the rough framing inspection. If your schedule has framing inspection in week six, your sprinkler subcontractor's drawings need to clear review before that, not after.
This is the part to plan around. A deferred submittal doesn't remove the review time. It moves it to a point where the project is already running, so a late package can idle a crew. Put the deferred items on your permit tracker with their own due dates. See how long a building permit is good for if a slow approval puts you near an expiration date.
Deferred submittal vs. plan check correction vs. revision
These get mixed up because they all involve more drawings after the first submission. They are different things.
| Deferred submittal | Plan check correction response | Revision | |
|---|---|---|---|
| When | After permit issuance | While the project is still in plan check | After permit issuance, for changes to the approved plans |
| What it is | A planned part of the design submitted later | Your reply to reviewer comments | An update to approved plans |
| Needs prior approval | Yes, from the building official | No | Per local procedure |
| Source | Menlo Park | Menlo Park | Menlo Park |
When
- Deferred submittal
- After permit issuance
- Plan check correction response
- While the project is still in plan check
- Revision
- After permit issuance, for changes to the approved plans
What it is
- Deferred submittal
- A planned part of the design submitted later
- Plan check correction response
- Your reply to reviewer comments
- Revision
- An update to approved plans
Needs prior approval
- Deferred submittal
- Yes, from the building official
- Plan check correction response
- No
- Revision
- Per local procedure
Source
- Deferred submittal
- Menlo Park
- Plan check correction response
- Menlo Park
- Revision
- Menlo Park
Menlo Park defines a resubmittal as a response to plan check comments on a project still under review, and a revision as an update to plans after a building permit has been issued. A deferred submittal is neither. It was always part of the plan, and the department agreed to see it later.
If a reviewer writes a correction asking you to "provide the missing system design," you may have deferred something you weren't allowed to defer. Answer it as a correction, following how to respond to a plan check correction letter, and ask whether the department will accept the item as a deferral instead. One forum poster argues that if missing information can change the basis for code approval it shouldn't be deferred. That is an opinion, not a rule, but it is how some reviewers think.
Riverside County notes that plan check review for revisions or deferred submittals may incur additional plan check fees. San Diego's information bulletin lists a separate deferred submittal processing charge. The amount differs between versions of the bulletin, so read the current fee schedule instead of copying a number from an old page.
Mistakes that cost time
- Deferring an item the department doesn't allow. Check the local list first.
- Leaving the item off the permit set's deferred list. Menlo Park and Rancho Cordova both expect it declared at application.
- Skipping the responsible designer's review. Lynnwood won't accept the package without it.
- Ordering material or starting install before approval. Wilsonville treats that as work without a permit.
- Tracking it nowhere. Nobody on the permit side sees a deferred item until an inspector asks for it. Keep it in the same log as your corrections. What is plan check correction tracking covers how teams do that.
Common questions
What is a deferred submittal in construction?
It is a portion of the design that is left out of the initial permit application and submitted for review after the permit is issued. The building official has to approve deferring it, and the work can't be installed until the department approves the package.
What items are typically deferred?
Prefabricated trusses, fire sprinkler and fire alarm plans, curtain wall and storefront systems, and elevator support rail show up on local checklists such as Kyle, Texas and San Diego. Your local department publishes the list that applies to you.
Who approves a deferred submittal?
Two parties. The design professional in responsible charge reviews the package for conformance with the building design before it is filed. Then the building department, or in some places the fire marshal, reviews and approves it.
Can a building department refuse to allow deferred submittals?
Yes. The Utah DFCM guidelines note that the building official is not required to allow them. San Diego stopped allowing deferred fire sprinkler submittals for all projects starting January 1, 2020.
How long does a deferred submittal review take?
It depends on the department. Newport Beach asks applicants to allow an average of two weeks for the first review of its deferred items. Check your department's published turnaround.
Is a deferred submittal the same as a permit revision?
No. A deferred submittal is planned from the start and approved for later filing. A revision changes plans that are already approved, after permit issuance.
Get permit notes like this by email
Practical notes from real plan-check cycles: what reviewers flag and how to get ahead of it. A few emails a month.
Unsubscribe anytime from any email.
Put every permit date on the calendar
Add the dates as tasks with an owner. Reminders go out 7 and 3 days before, the day before, and on the day.