Required Building Inspections for a New Residential House
Updated 7 min read
Short answer
The model code (IRC R109.1) lists footing, foundation, rough-in plumbing, mechanical, electrical and gas, frame, and final inspections. Cities add steps such as under-slab and insulation, so your permit's inspection list is the one that binds.
- Model code inspection types
- Footing, foundation, rough-in (plumbing, mechanical, electrical, gas), frame, final
- IRC R109.1
- Final inspection timing
- After the permitted work is complete and before occupancy
- Gig Harbor, WA amendment to R109.1
- Local additions
- Cities may require extra inspections depending on site conditions and scope
- Foxborough, MA inspections department
On this page (6)
The required building inspections for a new residential house follow the build order: footing, foundation, rough-in trades, framing, insulation and final. The International Residential Code (IRC) names the core types in Section R109.1. Your city adds its own steps and decides the exact list, and it prints that list on or with your permit.
This guide walks the sequence, says what each inspection checks, and shows which steps cities commonly add. It also covers the part that trips up schedules: the order in which approvals must come.
What the model code requires
IRC Section R109.1 establishes the required inspection types for one- and two-family dwellings. As summarized by Jaspector's IRC 2018 guide, those are:
- Footing
- Foundation
- Plumbing, mechanical, electrical and gas systems (rough-in)
- Frame
- Final
Subsection numbers and wording differ between sources and between editions, and local amendments rewrite them. Search results for this guide disagreed on which subsection holds the frame and final inspections, so check the section numbers in the edition your jurisdiction adopted. The five types above are consistent across the sources we read.
The building official can also require more inspections than the code lists.
The usual sequence, step by step
City handouts converge on one pattern. The wording below comes from published city pages, and each city's list is a minimum for its own permits.
1. Footing
The footing inspection happens after excavation and reinforcing steel are in place and before concrete goes in. Boise's residential inspection guide says it ensures the footing is properly placed and sized, that any reinforcing steel is installed, and that setbacks are verified against the city-approved (stamped) plans.
That last item matters for the site plan. If the footing is in the wrong place, the error is already in concrete once it is poured. If you haven't built a clean site plan yet, see our guide to the site plan for a building permit.
2. Foundation
The foundation inspection is a separate step in the model code. The Jaspector summary puts it after the anchor bolts are set and before framing or backfill. Some cities fold it into one visit with the footing, and others split it. Olathe, Kansas lists footing, foundation and under-slab plumbing, electrical and mechanical as required residential inspections, followed by garage floor slabs.
If your house has a slab, ask whether the city wants a separate under-slab inspection for the trades before you pour. Olathe does.
3. Rough-in plumbing, mechanical, electrical and gas
These inspections cover the systems that will be hidden behind walls and floors. Rexburg, Idaho schedules framing after the roof, masonry, framing, fire stopping, draft stopping and bracing are in place, and notes the rough-in trade inspections usually come before framing approval.
The National Association of Certified Home Inspectors makes the same point: the electrical, mechanical, gas and plumbing inspections must be completed and approved before the framing inspection. Trade permits are often pulled separately from the building permit, and they are inspected separately.
4. Framing
NACHI describes the framing inspection as usually the inspector's last chance to see everything that will be concealed inside the structure. Durham, North Carolina lists framing as its own required inspection after the foundation and slab inspections. Its framing check confirms that floor framing to the foundation is complete, including shims and squash blocking.
Rexburg's description adds that the framing inspection includes the house wrap. Don't hang drywall, and don't close any wall, until framing and the rough-ins have passed.
5. Insulation
Insulation is not one of the five core types in R109.1 as summarized above, but many cities schedule it as its own inspection. Fayetteville, North Carolina says insulation inspections are made after an approved framing and rough-in inspection and after the permanent roof covering is installed, with insulation and vapor retarders in place and before walls are closed. Richland County, South Carolina treats insulation as a separate inspection after the roughs pass.
If your jurisdiction does not list this step, the energy-code items may be checked at the framing or final stage. Read the permit card rather than guessing.
6. Final
The final inspection comes after the permitted work is complete and before occupancy. That wording appears in the Gig Harbor, Washington amendment to R109.1. Trade finals usually come first. Broken Arrow, Oklahoma describes its final building inspection as made after the building, yard and driveway are complete, and says the electrical, plumbing and mechanical finals should be approved before it.
Foxborough, Massachusetts says final building inspections may only be conducted after the plumbing, gas, electrical and fire finals are approved. Olathe states that all inspections must be complete before a certificate of occupancy (CO) or temporary certificate of occupancy is issued. For what that certificate is and how it differs from a certificate of completion, see certificate of occupancy vs certificate of completion.
Expirations slip when nobody owns the date. Track filing and permit dates with reminders →
Quick reference
| Stage | What the inspector looks for | Don't do this until it passes |
|---|---|---|
| Footing | Placement, size, reinforcing steel, setbacks against stamped plans (Boise) | Pour concrete |
| Foundation | Anchor bolts and foundation work in place (Jaspector, IRC 2018) | Frame or backfill |
| Under-slab (where required) | Trade lines below the slab (Olathe) | Pour the slab |
| Rough-in trades | Plumbing, mechanical, electrical, gas before concealment | Frame sign-off, cover walls |
| Framing | Concealed structural items, floor framing to foundation, house wrap (NACHI, Durham, Rexburg) | Insulate or close walls |
| Insulation | Insulation and vapor retarders in place (Fayetteville) | Hang drywall |
| Final | Completed work; trade finals approved first (Broken Arrow, Foxborough) | Occupy |
Footing
- What the inspector looks for
- Placement, size, reinforcing steel, setbacks against stamped plans (Boise)
- Don't do this until it passes
- Pour concrete
Foundation
- What the inspector looks for
- Anchor bolts and foundation work in place (Jaspector, IRC 2018)
- Don't do this until it passes
- Frame or backfill
Under-slab (where required)
- What the inspector looks for
- Trade lines below the slab (Olathe)
- Don't do this until it passes
- Pour the slab
Rough-in trades
- What the inspector looks for
- Plumbing, mechanical, electrical, gas before concealment
- Don't do this until it passes
- Frame sign-off, cover walls
Framing
- What the inspector looks for
- Concealed structural items, floor framing to foundation, house wrap (NACHI, Durham, Rexburg)
- Don't do this until it passes
- Insulate or close walls
Insulation
- What the inspector looks for
- Insulation and vapor retarders in place (Fayetteville)
- Don't do this until it passes
- Hang drywall
Final
- What the inspector looks for
- Completed work; trade finals approved first (Broken Arrow, Foxborough)
- Don't do this until it passes
- Occupy
What varies by city
Each of these differs from one jurisdiction to the next, and no model code settles them:
- The exact list. Foxborough states that its list is a minimum and that a project may need additional inspections depending on site conditions and scope.
- How inspections are requested and how far ahead you must call. Cities use phone lines, online portals or both. This is posted on the permit or the department's page.
- The local amendments. Cities adopt the IRC on their own schedule and change it.
To find the local list, start with the building department's inspections page, then your permit card or approved plan set. Our walkthrough on how to get a building permit shows where the inspection list sits in the process. For your city's own rules, see the jurisdiction pages under building permits, as one example.
Keeping inspections from stalling the job
An inspection that fails or gets skipped holds up everything that comes after it, since most work sequences are locked behind the previous approval. A few habits help.
- Make a one-page inspection list at permit issuance. Copy it from the permit card. Write each step next to the trade or crew that has to be ready for it.
- Track approvals as dated records. The record that matters is the date the inspector approved, not the date you requested it. You will want it for the final and for any dispute later.
- Don't cover anything until it passes. Each hidden-work step exists so the inspector can see it. Uncovering finished work to show it is slower than waiting.
- Close your corrections first. If plan check left open items, resolve them before the inspector arrives. How to respond to a plan check correction letter covers that process.
Common questions
What inspections are required for a new house?
The model code lists footing, foundation, rough-in plumbing, mechanical, electrical and gas, frame, and final (IRC R109.1). Cities add under-slab, insulation, and separate trade finals. Your permit lists the ones that apply.
What is the order of building inspections?
Generally footing, foundation, any under-slab trade work, rough-in trades, framing, insulation, then final. Several cities require the rough-in trades to pass before framing is approved, and the trade finals to pass before the building final.
Can I cover work before the inspector approves it?
No. The inspections exist to see work before it is concealed. NACHI notes the framing inspection is usually the last view of items that will be hidden in the structure. Covering work early can force you to open it up again.
Do I need an inspection for a small project like a deck or shed?
Often yes, if a permit is required, and sometimes no, if the project is exempt. Exemptions vary by city, so see deck building permit requirements and shed building permit.
Who has to be present at the inspection?
Requirements differ by jurisdiction, and we found no model-code rule on it. Check the instructions on your permit or the department's inspection page.
What happens if I fail an inspection?
Expect to correct the items the inspector lists and request a reinspection. Fees and rules for reinspections are set locally, so check your city's fee schedule rather than assuming.
Get permit notes like this by email
Practical notes from real plan-check cycles: what reviewers flag and how to get ahead of it. A few emails a month.
Unsubscribe anytime from any email.
Put every permit date on the calendar
Add the dates as tasks with an owner. Reminders go out 7 and 3 days before, the day before, and on the day.