How Long Does Plan Check Take? City Targets (2026)
Updated 7 min read
Short answer
Plan check targets published by cities run from a few days for simple work to about 30 days per cycle for larger projects. Resubmittals are usually shorter, but a poor submittal can reset the clock to the length of the first review.
- First review, new construction
- 15 business days
- Santa Cruz, CA target review dates
- Second review, new construction
- 10 business days
- Santa Cruz, CA target review dates
- Per-cycle review, commercial and residential
- 30 calendar days
- Palm Springs, CA plan review page
On this page (6)
How long does plan check take? It depends on your city, the project type and how many review cycles you need, but published targets are easy to find. Cities that post them give anywhere from a few business days for simple work to about 30 calendar days per cycle for larger projects. Resubmittals are usually reviewed faster than first submittals. Those numbers are targets, not promises, and every cycle of corrections adds another round on top.
This guide shows what real cities publish, why the same project can take twice as long in one place, what stretches a review, and how to build a schedule you can defend to a client.
What cities publish as plan check targets
Most building departments post turnaround targets by project type. The table below shows a sample from the pages we found. These are the cities' own estimates, and each one is subject to staffing and workload.
| City | Project | First review | Resubmittal | Source |
|---|---|---|---|---|
| Santa Cruz, CA | Standard new building construction | 15 business days | 10 business days | Santa Cruz target dates |
| Foster City, CA | New construction, standard track | 25 business days | 10 business days (revisions) | Foster City turnaround times |
| Foster City, CA | New construction, expedited track | 20 business days | 5 business days (revisions) | Foster City turnaround times |
| Berkeley, CA | Standard permit type | 30 working days | 15 working days | Berkeley estimated turnaround |
| Palm Springs, CA | Single-family, apartments, tenant improvements, commercial | 30 calendar days per cycle | Same per-cycle listing | Palm Springs plan review |
| Petaluma, CA | Commercial or multi-family | About 20 to 30 business days | About 10 business days | Petaluma plan check FAQ |
| Mountain View, CA | Single-family homes and duplexes | 3 business days | Not listed in our results | Mountain View permit timelines |
Santa Cruz, CA
- Project
- Standard new building construction
- First review
- 15 business days
- Resubmittal
- 10 business days
- Source
- Santa Cruz target dates
Foster City, CA
- Project
- New construction, standard track
- First review
- 25 business days
- Resubmittal
- 10 business days (revisions)
- Source
- Foster City turnaround times
Foster City, CA
- Project
- New construction, expedited track
- First review
- 20 business days
- Resubmittal
- 5 business days (revisions)
- Source
- Foster City turnaround times
Berkeley, CA
- Project
- Standard permit type
- First review
- 30 working days
- Resubmittal
- 15 working days
- Source
- Berkeley estimated turnaround
Palm Springs, CA
- Project
- Single-family, apartments, tenant improvements, commercial
- First review
- 30 calendar days per cycle
- Resubmittal
- Same per-cycle listing
- Source
- Palm Springs plan review
Petaluma, CA
- Project
- Commercial or multi-family
- First review
- About 20 to 30 business days
- Resubmittal
- About 10 business days
- Source
- Petaluma plan check FAQ
Mountain View, CA
- Project
- Single-family homes and duplexes
- First review
- 3 business days
- Resubmittal
- Not listed in our results
- Source
- Mountain View permit timelines
Two patterns show up. First, the range is wide: Walnut Creek says a first review can take anywhere from 8 to 28 business days depending on project type, per its turnaround times page. Second, the unit matters. Business days skip weekends and city holidays. Calendar days do not. A "30 day" target in one city and a "30 working day" target in another are not the same schedule.
Note: Every city counts differently. Some start the clock at application intake, others when the application is deemed complete or paid. Read the footnotes on the page before you quote a number to a client.
Why plan check takes longer in some cities
Published targets assume a complete submittal and normal workload. Four things move the actual time.
Routing. Plans that go to fire, engineering or planning pick up time. Belvedere notes that large projects often need multi-department review before a permit can issue, in its plan check FAQ. Coral Springs, Florida lists paper plan review at up to 15 days because plans are routed by hand between departments, versus up to 7 days when all disciplines review electronically at once. See its plan review process page.
Project size and complexity. Irvine's published answer allows more time for large or complicated projects, per its plan check FAQ.
Submittal quality. Salinas says that substantially incomplete projects are returned before submittal, and that when a poor submittal needs another review, the next cycle equals the time of the first review. See the Salinas turnaround times. That rule turns a 10-day resubmittal into a second full-length review.
Staffing and workload. Raleigh describes its review benchmarks as goals, not guaranteed turnaround times, on its turnaround and dashboards page. The practical read: a target is the city's aim, and you should add a margin.
Expirations slip when nobody owns the date. Track filing and permit dates with reminders →
Faster tracks: over-the-counter and expedited review
Many departments offer a quicker path for smaller projects. If your work qualifies, it can cut weeks from the schedule.
- Over-the-counter review. Santa Cruz lists over-the-counter review at 1 to 5 working days, and Berkeley's over-the-counter option is next-day, per the pages linked above.
- Express or small-project programs. Raleigh's Commercial Pony Express Review covers alterations up to 10,000 square feet, with an initial review of five business days and additional reviews of three. Details are on its Pony Express page.
- Paid expedited review. Riverside says expedited plan review services may be available for an additional fee, per its plan review page. Foster City's expedited track, in the table above, shows the effect: 20 business days against 25 for new construction.
Each of these has eligibility rules and often a fee. Ask the permit center whether your scope qualifies before you design the schedule around it. If your project is large enough that a permit expediter is worth considering, ask them which tracks the city actually grants.
How many review cycles to plan for
Plan check rarely ends after one pass. A first review produces a correction letter, you revise, and the city reviews again. Raleigh's September 2025 presentation to its development advisory committee describes a re-review fee triggered when Building requires a resubmittal after the second review cycle, a policy it calls an existing fee now applied consistently. That is one city's rule, but it shows why a third cycle is expensive in both time and money.
A defensible schedule for a client looks like this:
- Take the city's first-review target for your project type.
- Add your own time to respond. Raleigh's Express Review gives applicants three business days to return a revised set, which shows how short the window can be on fast tracks. Standard tracks are less strict, but your design team still has to turn comments around.
- Add the city's resubmittal target.
- Decide whether to plan a third cycle. If the project routes to several departments, assume you may need one.
- Add the time for permit issuance and fee payment after approval.
Santa Cruz's published numbers give a concrete example for standard new building construction: 15 business days for the first review plus 10 for the second is 25 business days of city time. It does not include your response time or issuance. The same arithmetic with Foster City's standard track gives 35 business days, and with Berkeley's standard permit type, 45 working days.
How to shorten the cycle
You can't control the city's queue. You can control what lands in it.
- Check the submittal list first. Confirm which divisions get your plans and what each one requires. Plans stalled waiting on a fire or engineering sign-off are a common complaint in consultant writing, such as this JDJ Consulting article. Treat that as practitioner advice, not measured data.
- Submit a complete set. Missing sheets, unsigned drawings and absent calculations stop reviews or hold up routing to other departments. See the broader how to get a building permit steps for what to gather first.
- Respond to every comment, in order. Responses that don't clearly address prior comments add review cycles, because reviewers have to repeat themselves. Our guide to responding to a plan check correction letter covers the format.
- Ask for a pre-submittal meeting where the department offers one.
- Track the clock yourself. Write down the submittal date, the target date and the date each comment set came back. A shared tracker beats a memory of an email. The correction tracking overview explains the idea, and Olumba's permit tracking can hold those dates per project if you don't already have a place for them.
Common questions
What is plan check?
Plan check, also called plan review, is the building department's review of your drawings for code compliance before it issues a permit. The reviewer sends corrections, you revise and resubmit, and the cycle repeats until the plans are approved.
How long does plan check take for a residential project?
It depends on the city and scope. Mountain View lists 3 business days for single-family homes and duplexes, Palm Springs lists 30 calendar days per cycle, and Walnut Creek's first-review range runs from 8 to 28 business days. Check your own department's posted targets.
How long does a plan check resubmittal take?
Cities that publish both numbers usually list the resubmittal as shorter: 10 business days against 15 in Santa Cruz, 15 working days against 30 in Berkeley. Salinas is the exception to watch for: a resubmittal caused by a poor submittal gets the same time as the first review.
Can you speed up plan check?
Sometimes. Over-the-counter review, small-project programs and paid expedited tracks exist in a number of cities, and a complete, well-organized submittal avoids extra cycles. Eligibility and fees are set locally, so ask the permit center.
Do the targets guarantee a date?
No. Raleigh calls its benchmarks goals, not guaranteed turnaround times, and other cities describe their figures as estimates that shift with workload. Build a margin into any client schedule. For more on pricing and process questions, see the FAQ.
Get permit notes like this by email
Practical notes from real plan-check cycles: what reviewers flag and how to get ahead of it. A few emails a month.
Unsubscribe anytime from any email.
Put every permit date on the calendar
Add the dates as tasks with an owner. Reminders go out 7 and 3 days before, the day before, and on the day.