Plan Check Resubmittal Checklist: What Cities Ask For

Updated 7 min read

Short answer

A complete plan check resubmittal usually has a response letter answering every comment, revised drawings with changes clouded and tagged, and any required checklist or forms. Without the letter, cities like Danville treat the package as incomplete.

Resubmittal without a response letter
Package is incomplete
Town of Danville handout
Paper sets for a 20+ sheet package
2 wet-signed complete sets plus 1 extra
City of Alameda handout
Changes not tied to a comment
Separate narrative letter
City of Milpitas
On this page (8)
  1. What goes in a plan check resubmittal package?
  2. What a response letter has to contain
  3. How to mark the revised drawings
  4. Changes nobody asked for
  5. Where four cities differ
  6. Timing and sequencing
  7. A pre-submittal self-check
  8. Common questions

A plan check resubmittal is the package you send back to the building department after a correction letter. Most cities want three things in it: a response letter that answers every comment, revised drawings with each change clouded and tagged, and whatever checklist or form the city attaches to resubmittals. Leave out the letter and some cities, including Danville, treat the whole package as incomplete.

There is no single national checklist. Each department writes its own, and they disagree on set counts, delivery method and even whether you resubmit only the changed sheets. What they agree on is the core. This guide lays out that core, then shows where four city handouts differ so you know what to look up before you upload anything.

What goes in a plan check resubmittal package?

Start with the city's own resubmittal handout. Search the department's site for the permit type and "resubmittal", because many cities keep it separate from the initial submittal checklist. Then build the package in this order.

  1. Response letter. One letter per reviewing department, or one letter that is organized by department. Each correction gets its own numbered response.
  2. Revised drawings. The sheets that changed, or the whole set, depending on the city. Clouds around every change, a delta tag tied to a revision entry, and an updated title block.
  3. Revised calculations, reports and specifications. Anything a comment touched. Structural calcs, energy compliance forms and soils reports are the usual ones.
  4. The city's resubmittal checklist or form, if it has one. Some require the applicant's signature.
  5. A narrative for any change nobody asked for. More on this below.
  6. Fees, if the city charges for rechecks. Check the fee schedule rather than assuming.

Before you assemble it, get the original correction letter and every reviewer's markup in one place. If a department sent comments separately from the main letter, a response letter that covers only the main letter will draw a second round.

What a response letter has to contain

Cities are consistent about this part. Danville's guideline asks for an itemized list showing how each comment was handled and where the change appears on the plans, specifications or calculations. Its sample letters are dated, addressed to the Building Division, cite the initial comment letter and carry the permit number. Repeating the original comment in your response is optional there.

Milpitas asks for response letters with a response to each comment for each review discipline, and the letter has to show which details, specifications or calculations carry the required information. Lynnwood's version asks for the correction item from the markup summary, the plan page number or label, and the response itself, per its comment response letter guidance.

Put together, each line of your letter needs four things:

ElementExample
Comment numberStructural 3
Original comment (optional in some cities)Show hold-down at grid C
Your responseHold-down added; see detail 5/S3.1
Where to find itSheet S3.1, detail 5; calc page 12

Comment number

Example
Structural 3

Original comment (optional in some cities)

Example
Show hold-down at grid C

Your response

Example
Hold-down added; see detail 5/S3.1

Where to find it

Example
Sheet S3.1, detail 5; calc page 12

Answer with a location, not an assurance. "Revised as requested" forces the reviewer to hunt. "Panel added to Detail 3/A.1" lets them confirm in seconds. If you disagree with a comment, say so in the response, cite the code section you are relying on, and attach whatever supports your reading. Reviewers can accept a reasoned disagreement. They can't accept silence.

For a fuller walkthrough of the letter itself, including how to handle comments you want to push back on, see how to respond to a plan check correction letter.

Retyping the correction letter is the slow part. Parse your correction letter free →

How to mark the revised drawings

Alameda's electronic submittal handout says to cloud all changes and note the delta number on the title block. Geocivix, a plan review software vendor, advises updating the revision block or date on affected sheets so reviewers can see what moved, according to its help article on responding to corrections. One industry guide in the same search results names revision clouds, numbered delta triangles and revision entries in the title block, but it describes that as practice, not a jurisdiction rule.

A workable routine:

  1. Cloud every change, including changes you made that no comment asked for.
  2. Put a numbered delta tag on each cloud and add a matching entry to the revision schedule.
  3. Update the revision date in the title block on every sheet that changed.
  4. Check that the sheet index still matches the set. New sheets get listed; deleted sheets get removed.
  5. Flatten and name files the way the city specifies. Lynnwood, for one, publishes electronic submittal standards and naming conventions.

Changes nobody asked for

You will change things between rounds that no reviewer mentioned. A client moves a wall. A consultant updates a detail. Cities want to hear about it.

Milpitas requires a separate letter with a detailed narrative identifying the sheet number and the changes made. Lynnwood asks you to identify changes the city did not require, since unreviewed changes may add time and fees. The reasoning is simple: a reviewer who finds an unmarked change has no way to trust the rest of the set.

If a change affects work that another discipline already approved, flag it in that discipline's section too. A mechanical change that moves a shaft is a structural comment waiting to happen.

Where four cities differ

These handouts show how much the details vary. Read them as examples, not as your city's rules.

CityResponse letterSet counts and deliveryNotable requirement
Danville, CAMandatory; no letter, no submittalIn person: 2 copies of the letter, 3 sets of revised drawings, 2 sets of supporting documents. Online: upload to the permit's Attachments pageSamples include general and structural-only formats
Alameda, CAExplain how each comment from every department was addressedPaper handout: under 20 sheets, 2 wet-signed copies of revised sheets plus 1 extra set per commenting department; 20 or more, 2 wet-signed complete sets plus 1 extraRespond to all departments in one resubmittal; schedule an appointment first
Milpitas, CAOne response per comment, per disciplineThrough ProjectDoxComplete drawing set, not only changed sheets
Lynnwood, WARequired; not accepted without a written responsePermit portal uploadFlag changes the city did not require

Danville, CA

Response letter
Mandatory; no letter, no submittal
Set counts and delivery
In person: 2 copies of the letter, 3 sets of revised drawings, 2 sets of supporting documents. Online: upload to the permit's Attachments page
Notable requirement
Samples include general and structural-only formats

Alameda, CA

Response letter
Explain how each comment from every department was addressed
Set counts and delivery
Paper handout: under 20 sheets, 2 wet-signed copies of revised sheets plus 1 extra set per commenting department; 20 or more, 2 wet-signed complete sets plus 1 extra
Notable requirement
Respond to all departments in one resubmittal; schedule an appointment first

Milpitas, CA

Response letter
One response per comment, per discipline
Set counts and delivery
Through ProjectDox
Notable requirement
Complete drawing set, not only changed sheets

Lynnwood, WA

Response letter
Required; not accepted without a written response
Set counts and delivery
Permit portal upload
Notable requirement
Flag changes the city did not require

Alameda's own pages do not fully agree with each other. The paper handout says responses are submitted in person, while the "How to Respond to Plan Check Comments" page points to an online portal. If the handouts you find conflict, ask the permit technician which applies to your project. Don't pick the one you like.

Note: Set counts, delivery methods and fees change often. Confirm them with the department on the day you submit, and keep the confirmation.

Timing and sequencing

Two timing rules show up in these handouts and trip people up.

First, don't resubmit early. Alameda says all reviewing departments must complete their review before you can resubmit, and it asks you to wait for the hold notice email. A resubmittal that arrives while one department is still reviewing can be bounced or split.

Second, ask about deadlines before they pass. Geocivix notes that extensions are commonly granted when you ask early and rarely when you ask late. If a consultant is late, call the permit center before the due date, not after.

For how long the next round should take once you have resubmitted, see how long plan check takes. If your resubmittal depends on an item the city agreed to review after permit issuance, deferred submittals follow a different path from corrections.

A pre-submittal self-check

Before you upload, read the package once as the reviewer would.

  • Does every comment from every department have a response, including comments in separate emails or markups?
  • Can you find each response on the sheet it names, inside a cloud?
  • Does the revision schedule list every delta, and does each delta have a cloud?
  • Do calculations and drawings agree on the revised values?
  • Did you list every change nobody asked for?
  • Are file names, set counts and signatures what the city's handout asks for?
  • Is the city's checklist or form signed, if it requires one?

Keeping a comment list with a status next to each item makes that check mechanical. A spreadsheet works. So does a tool that parses the letter into line items, such as the one in Olumba's correction tracking, if you run several permits at once.

Common questions

Do I resubmit the whole set or only the changed sheets?

It depends on the city. Milpitas says the complete drawing set listed in the index must be in the resubmittal package. Alameda's paper handout accepts revised sheets for smaller packages. Read the city's handout for your permit type.

Is a response letter required?

In many cities, yes. Danville says a package without a response letter is incomplete and can't be submitted. Lynnwood does not accept a resubmittal without a written response summarizing all revisions. Even where it is not required, a letter gets you through review faster than a pile of clouded sheets.

What if I disagree with a plan check comment?

Say so in the letter, cite the code section you are relying on, and point to the supporting sheet or calculation. Don't ignore the comment or silently leave the drawing unchanged. Many departments will also talk through a disputed comment by phone or at an appointment before you resubmit.

What do I do about changes the reviewer didn't ask for?

List them. Milpitas wants a separate narrative letter that gives the sheet number and describes each change. Lynnwood says unreviewed changes may add time and fees, so identify them up front.

Can I resubmit if one department hasn't finished reviewing?

Usually not. Alameda says all reviewing departments must finish before you resubmit, and to wait for its hold notice email. Ask the permit center how your city handles partial reviews.

Get permit notes like this by email

Practical notes from real plan-check cycles: what reviewers flag and how to get ahead of it. A few emails a month.